#1
|
|||
|
|||
BCWP, BCWS show zero
This question has been asked before but the answers that have been given are not solving the problem. All I see in the BCWS and BCWP columns are zeros. Let me forestall some of the usual responses to this complaint:
1) I did create resources with cost rates. 2) I did assign resources to tasks. 3) I did save the baseline. 4) I set the EV method to percent complete for some tasks and physical % complete for others. I entered corresponding values for % complete and physical % complete for each task. 5) I did set a status date in the middle of the project when some tasks should be completed, some partially completed and some not started. 6) I did update the project. 7) I have positive values for Baseline Cost, ACWP, Remaining Cost, Cost Variance, but the BCWS and BCWP columns stubbornly remain zero. |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
PPT show did not show up | Jaysne | PowerPoint | 0 | 03-03-2014 09:00 PM |
Question: Hyperlink to other show, but close the current show | habibfikri | PowerPoint | 0 | 12-26-2010 02:37 AM |
PP 2010 .avi file plays during slide show, but causes the slide show to loop to begin | VictorS | PowerPoint | 0 | 10-16-2010 10:23 AM |
if (neg) show 0 | ram1000 | Excel | 2 | 09-16-2008 02:30 PM |
Show As | Tos | Outlook | 0 | 07-08-2008 10:56 AM |