BCWP, BCWS show zero
View Single Post
05-02-2014, 09:46 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Do you have values in BCWS and BCWP for some tasks and not others? By default Project calculates EV data based upon % complete and Baseline. Do you have SP-1 installed to Project 2013?