preetsp preetsp is offline Resources not showing 8 hrs per day Windows 7 64bit Resources not showing 8 hrs per day Office 2007
Novice
Resources not showing 8 hrs per day
 
Join Date: Apr 2014
Posts: 5
preetsp is on a distinguished road
Default Resources not showing 8 hrs per day

Hi,

I am using Project 2007. I set the calendar such that resources work 8 hrs a day. However, there are days when the resource shows only 2 hrs. These days are highlighted in red in the Resource Usage view.



The resources have Max Units as 100%.

Can someone pls tell me the reason for this?

Thanks,
Preeti.
Reply With Quote
  #2  
Old 04-21-2014, 06:32 AM
JulieS JulieS is offline Resources not showing 8 hrs per day Windows 7 64bit Resources not showing 8 hrs per day Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

If the task starts at the end of the day, the resource will only work 2 hours. What time does the task begin or end?
Reply With Quote
  #3  
Old 04-21-2014, 09:52 PM
preetsp preetsp is offline Resources not showing 8 hrs per day Windows 7 64bit Resources not showing 8 hrs per day Office 2007
Novice
Resources not showing 8 hrs per day
 
Join Date: Apr 2014
Posts: 5
preetsp is on a distinguished road
Default

Thanks Julie.

I read one of your earlier replies and realized that Project considers units and not work, in the Resource Usage view.

So even though the resources are working on 2 tasks for a total of less than 8 hrs, they are shown as over allocated as they are utilizing 100% of their units for each task.

Regards,
Preeti.
Reply With Quote
  #4  
Old 04-22-2014, 06:42 AM
JulieS JulieS is offline Resources not showing 8 hrs per day Windows 7 64bit Resources not showing 8 hrs per day Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Correct. Project says that if a resource is assigned to multiple tasks and the sum of the assignment units (Peak Units) is above the resource's maximum units - they are overallocated.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resources not showing 8 hrs per day Resources pool showing file name grazi Project 2 04-04-2014 11:12 AM
Resources not showing 8 hrs per day Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Resources not showing 8 hrs per day How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM
Resources not showing 8 hrs per day Total Resources 602chrislys Project 1 10-04-2010 09:04 AM
Assigning resources. Sergey M Project 0 01-25-2006 09:33 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:20 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft