#1
|
|||
|
|||
|
Yes, I do. When the resource is assigned to more than one task in the timeframe, the percent allocation value does not roll up to the project level. I do not know why. The best I can suggest is to see if you can copy/paste the data out to Excel and perform the calculations there if using the Work value isn't sufficient. |
|
#2
|
|||
|
|||
|
It 'a shame it does not work!
I'll do it in excel, thank you Julia for your support (perhaps in Project 2007 it worked) http://forums.techarena.in/microsoft...ct/1104057.htm Last edited by codeghi; 04-25-2014 at 02:18 PM. |
|
#3
|
|||
|
|||
|
Actually the Resource Group filter still works in Project 2010 - the Percent allocation rolls up to the group level. The resource group is resource field, while we are using Project as an assignment group.
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
MS Project 2013 - Overview report error
|
Imagios | Project | 15 | 02-05-2016 09:21 AM |
Can I create a report that shows the health of a project?
|
bilbo52 | Project | 1 | 02-22-2014 07:04 AM |
Who Does What When report in Project 2013
|
Smithy15 | Project | 1 | 01-20-2014 08:48 AM |
resource leveling in ms project
|
ketanco | Project | 1 | 12-24-2011 12:58 PM |
| MS Project Resource Chart | fherbert | PowerPoint | 0 | 09-09-2010 12:20 PM |