Old 04-11-2014, 03:36 PM
Raviwildcat Raviwildcat is offline Copying indicators from project to excel Windows 8 Copying indicators from project to excel Office 2010 32bit
Novice
Copying indicators from project to excel
 
Join Date: Apr 2014
Posts: 2
Raviwildcat is on a distinguished road
Default Copying indicators from project to excel

Hi everyone I'm new to the board!

I'm much more comfortable in MS-Excel than I am in MS-Project. I'd like to place some tasks from my MS-Project into Excel so I can put in pivots, create custom summary tables etc.



I'm having trouble copying into excel though - I can't capture the indicators field. So, although when I look at the project in Excel, I can't tell which tasks have completed, which are 75% done etc. without looking at the original MS-Project file.

Is there a way to copy over the indicators tab?

Thanks,
Ravi
Reply With Quote
  #2  
Old 04-11-2014, 05:28 PM
JulieS JulieS is offline Copying indicators from project to excel Windows 7 64bit Copying indicators from project to excel Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Do you mean the indicators field? As far as I know, those graphics do not come over through a copy/paste.

Insert the % complete field and use that as a much more reliable indicator of progresss.
Reply With Quote
  #3  
Old 04-11-2014, 05:39 PM
Raviwildcat Raviwildcat is offline Copying indicators from project to excel Windows 8 Copying indicators from project to excel Office 2010 32bit
Novice
Copying indicators from project to excel
 
Join Date: Apr 2014
Posts: 2
Raviwildcat is on a distinguished road
Default

Hi Julie - that's an excellent idea. Thank you!

Ravi
Reply With Quote
  #4  
Old 04-13-2014, 07:39 AM
JulieS JulieS is offline Copying indicators from project to excel Windows 7 64bit Copying indicators from project to excel Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome and thanks for the feedback.
Reply With Quote
Reply

Tags
excel 2010, project 2010



Similar Threads
Thread Thread Starter Forum Replies Last Post
Copying indicators from project to excel Excel 2003 VBA Help copying innertext Liquid Excel Programming 2 04-08-2014 05:14 AM
Copying data from Project to Excel OTPM Project 13 12-20-2013 10:25 AM
Copying indicators from project to excel Copying and pasting from Excel Lorna B Word 1 03-20-2012 11:58 PM
Copying indicators from project to excel Copying text from Excel to Word Fossils13 Office 1 02-22-2010 08:39 PM
Copying indicators from project to excel MS Excel 2004 for Mac - copying dates between documents BCRenton Excel 4 11-10-2009 07:28 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:54 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft