You can create task calendars (as it sounds like you may have) to restrict the scheduling of the tasks to their respective days. By assigning the task calendars, the task will be scheduled only for those days. To assign the task calendar, show the Task Information (right click) and set the Task Calendar on the advanced tab.

However, the display of non-working time (default gray shade) is set for the entire Gantt chart - you cannot show only Tuesday/Wednesday on Course 5 and Thursday/Friday on Course 6.

I personally would turn off the display of non-working time as your definition is variable.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Contact view filter not working gebobs Outlook 2 03-10-2014 06:28 AM
How can I fix a print view problem that causes it to stop working.. Excel 2007, Vista birdie123 Excel 0 08-18-2012 12:02 PM
non working day view How to save a PPT file in 'Reading View' to be opened always in 'Reading View' ItzVickey PowerPoint 2 08-08-2012 09:23 AM
non working day view Separate projected view vs. PC view possible? frank14612 PowerPoint 3 02-19-2012 02:43 AM
non working day view How do I view a document in "normal" view... JennK13 Word 4 08-15-2011 11:19 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:42 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft