I have created a Labour number using a Text Field.
When using the View Task Usage with the Group by command using the Labour Number the summary values are not being shown for the Labour Numbers. When I was using Project 2003 it showed the summary values, now I have been upgraded to 2010 it does not. do I need to tick a Option box of some kind ? Thank you Glenn Task NameLabour NoSummaryStartFinishRemaining WorkWork% Work CompleteLabour No: A2471100A2471100Yes0%Labour No: A2471200A2471200Yes0% |
#2
|
|||
|
|||
![]()
What summary values are you looking for?
Is the labour number a task or resource value? Are you filtering or grouping? Filtering will not just show any summary values for the visible tasks. However, grouping should. Please tell us a bit more about your custom field and answer the questions above. Can you attach a picture of what you are seeing and describe better what you expect to see? |
#3
|
|||
|
|||
![]()
Julie
Please see attached example I am using the Grouping command (Not a Filter) using Text 1, I need to see total work, %Complete for Groups A,B and C in Text 1. I could do this using 2003 also a colleague using 2010 is able to sum the group selections. For the life of me I cannot find a tick box to total the groups. Thank you Regards Glenn |
#4
|
|||
|
|||
![]()
I too was seeing the same issue. I just downloaded and installed the latest CU and it now works.
http://support.microsoft.com/kb/2925785 |
#5
|
|||
|
|||
![]()
Julie
Thanks for your help, I have notified our Help Desk to load the latest CU. Regards Glenn |
#6
|
|||
|
|||
![]()
Great. Keep us posted as to the progress.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
'Group By' Summary Duration Incorrect | hmcleay | Project | 3 | 03-01-2013 05:40 AM |
![]() |
tmanzan | Project | 7 | 01-15-2013 12:45 PM |
![]() |
ketanco | Project | 1 | 01-02-2012 02:34 PM |
Task and Summary Durations | JR_12 | Project | 0 | 10-15-2011 05:07 PM |
Accessing Assignment Detail Data in Task Usage View | CGM3 | Project | 0 | 10-05-2010 05:56 AM |