Project does not know of any modified working schedule unless you tell it so. The default calendar used in Project for scheduling is the Standard calendar where work is defined as 08:00 - 12:00, 13:00 - 17:00 Monday through Friday.
When you enter a duration of 9 days - project will count 9 working days based upon the calendar. So if the task starts on Monday March 17 it will end on Thursday March 27.
You need to modify the calendar (Change working time) and then you will see the gray shade in the Gantt chart showing the changed working time.
If you need more details on changing the calendar, post back.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
modified styles showing in style list GinnyB Word 5 04-04-2013 03:04 AM
Modified Signature Line in Microsoft Word gurp99 Word 0 03-28-2012 09:58 AM
Modified work cycle print modified date guice Word 1 03-23-2011 07:29 PM
How To Open Documents in Date Modified Order diver9 Word 0 08-29-2010 03:34 AM
Modified work cycle Stuck in cycle of name/password dialogue box originale Outlook 18 09-25-2009 03:02 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:15 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft