Hi
I am struggling with a DateDif function. I want to be able to identify those tasks that are scheduled to finish within 3 days of the current date. Here is what I have tried so far: IIf(Date()-[Finish]>"0" And Date()-[Finish]<="3","TRUE","FALSE") IIf(DateDif("d",[Finish],Date())>"0" AND DateDif("d",[Finish],Date())<="3","TRUE","FALSE") However neither works. I am sure I am close but cant see the issue. Any help appreciated. Thanks Tony |
|
![]() |
||||