  #5  
Old 03-07-2014, 04:47 PM
JulieS JulieS is offline Project Hours Windows 7 64bit Project Hours Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Do your human resources work 20 hours per day or only the space? If your resources' calendars only allow 8 hours per day - the 32 hours will go to the next day - even if the space allows 20 hours of work per day.

What time does the task start?

Please describe the following:
Working time for the room calendar.
Working time for the human resources.
Starting date/time for the task.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Hours Hours in MS Project Changed ayeh Project 14 02-12-2014 10:41 AM
MS Project-timescale in hours John Franklin Project 5 10-30-2013 08:41 AM
Project Hours How to add hours together PomDave Excel 3 09-05-2011 04:43 AM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM
Error 9571 when opening Project Server from Project Pro mona Project 0 04-24-2007 07:50 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:57 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft