#1
|
|||
|
|||
Is my Milestone working that way it's suppose to?
I am attaching a print screen of the project I am working on as I ran into a milestone wrapping back to left side of gantt chart when I think it's suppose to be at the end of a completed set of tasks on the right side where the finished tasks end? I am using MS Project 2007. See attachment. Thx
Last edited by Enuhseh207; 02-22-2014 at 07:17 PM. Reason: Forgot to id ms project version |
#2
|
|||
|
|||
The task is complete as indicated by the blue check mark. Once a task has been marked complete - it no longer follows predecessor data. Double click on the task and on the General tab - set the % complete to zero.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
WORDART is not working as it should/has | kirkdogg55@hotmail.com | Word | 4 | 08-23-2013 12:13 AM |
working 4 10's, need help to set up | rkirkland | Project | 1 | 12-19-2012 02:47 PM |
Word is not working right. | Ham | Word | 3 | 11-04-2012 01:49 PM |
Milestone durations | fraserm | Project | 4 | 01-13-2012 08:43 AM |
Project 2010 - Milestone Font Colour | OTPM | Project | 1 | 05-11-2011 03:22 AM |