#2
|
|||
|
|||
![]()
The task is complete as indicated by the blue check mark. Once a task has been marked complete - it no longer follows predecessor data. Double click on the task and on the General tab - set the % complete to zero.
|
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
kirkdogg55@hotmail.com | Word | 4 | 08-23-2013 12:13 AM |
![]() |
rkirkland | Project | 1 | 12-19-2012 02:47 PM |
![]() |
Ham | Word | 3 | 11-04-2012 01:49 PM |
Milestone durations | fraserm | Project | 4 | 01-13-2012 08:43 AM |
Project 2010 - Milestone Font Colour | OTPM | Project | 1 | 05-11-2011 03:22 AM |