Cycat Cycat is offline Levelling resource's units to calculate duration task Windows 7 32bit Levelling resource's units to calculate duration task Office 2010 32bit
Novice
 
Join Date: Feb 2014
Posts: 3
Cycat is on a distinguished road
Default

For a similar situation, but this time David has from time to time tasks which will not take him 100% - sometimes 20%, sometimes 50%.
But he also has tasks which don't have limitation of Units, and can be advanced any time that he is available.

Is there any method to overcome Project's inability to automatically lower Units while prolonging the tasks length?
(This time there is no constant Unit value that can be used as it was with Giovanni's 75%.)

Thanks!
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Levelling resource's units to calculate duration task Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Levelling resource's units to calculate duration task Linking task duration to another task branchi Project 1 08-15-2013 06:03 AM
Levelling resource's units to calculate duration task MS Project - Maximizing resource levelling aguatorito Project 3 03-10-2013 06:08 AM
Levelling resource's units to calculate duration task How to use fixed duration, fixed work and have resources/units leveled automatically? Joeb Project 3 06-25-2012 04:18 PM
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:29 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft