JulieS JulieS is offline How to calculate edays? Windows 7 64bit How to calculate edays? Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I assure you, Project is very good at math.

As I have tried to explain, you have a mismatch between your Project calendar (Project Ribbon, Change Working time) and your definition of a day and week. Zooming in to the Gantt chart is not a substitute for looking at both your options settings (File > Options, Schedule) and your calendar.

So - what is your working time in your calendar. (Please check - Project Ribbon, Change Working time.)

What is your definition of day and week - File > Options, Schedule.
What is your default start time?
What is your default end time?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Macro to calculate a value of a checkbox. stephen_ Excel Programming 1 06-27-2012 04:57 PM
calculate age userman Excel 8 06-02-2012 10:59 PM
How to calculate edays? How to calculate percentages??? fabthi Excel 3 04-13-2012 12:08 PM
Can't calculate formulas Cpat Excel 2 06-09-2010 02:07 PM
How to calculate edays? How to get cells to calculate time? jrasche2003@yahoo.com Excel 2 02-09-2007 07:10 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:25 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft