![]() |
#5
|
|||
|
|||
![]()
ok and, work is always entered in hours right?
we do not and can not enter sf or sf / day etc correct? so in other words, i enter 40 hours because i calculate it outside of ms project myself... correct? |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
updating not completed tasks or 0% tasks | ketanco | Project | 3 | 08-24-2012 05:59 AM |
Which .pst is the correct .pst | dbsoccer | Outlook | 1 | 04-08-2012 12:12 PM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
![]() |
Jamal NUMAN | Word | 3 | 04-17-2011 05:35 PM |
So what is the correct value of PONT_STRING anyway? | DrDOS | Outlook | 0 | 11-21-2010 04:30 AM |