As far as I know, you cannot link to a GUID instead of a task ID. What precisely are you using the master project for?
|
|
#2
|
|||
|
|||
|
Hi Julie
The Master Project picks up all of the key Milestones from all of the sub projects. Normally I would consolidate and filter on Milestones but they want the Master in a pre-defined format and layout. Tony |
|
#3
|
|||
|
|||
|
Is it possible to create a template for the master project and then just create the master project each time for reporting?
|
|
#4
|
|||
|
|||
|
Hi Julie
I already have the master template but I still have the issue of linking each of the 12 workstreams key milestones to the master template. |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| MS Project Master Plan remebers old version of subproject | Sisse.hee | Project | 1 | 01-22-2014 09:03 AM |
For multiple word document management, is it possible to enable or disable plugin ??
|
anfas | Word | 2 | 11-21-2013 10:23 PM |
Columns - separate management
|
alvin | Word | 1 | 09-18-2012 09:02 AM |
| Connectivity issue of Project Professional with Project Server | kashif | Project | 0 | 03-27-2009 06:37 AM |
| Error 9571 when opening Project Server from Project Pro | mona | Project | 0 | 04-24-2007 07:50 AM |