#1
|
|||
|
|||
![]()
To add on to Golouseus's excellent answer, after displaying the Task Form in the lower pane, click the in the Task Form and on the Task Form Format ribbon, choose Predecessors and Successors to view that information for the selected task.
|
![]() |
|
![]() |
||||