#1
|
|||
|
|||
![]()
Hello All,
Same project, same schedule in MSP that I was inquiring about before... To recall, this is a schedule that's been updated by our local team in another country and is sent to me weekly to produce progress reports. First 25 lines or so are all milestones acting as a de facto high level summary of the schedule. It was created mainly for the management so when they look at it, they can easily take it all in, without going through other 300+ lines. Against my ongoing pleas, the local project team puts constraints (Start No Earlier Than) on all the milestone tasks, both in the "summary" and the rest of the schedule. The summary tasks and the corresponding schedule tasks are connected via predecessor/successor relationships. Interestingly enough, I noticed that last time when I got the updated file from them, updated the project status date (for whatever reasons the local team can't get this function to work so I do it form here), and hit Update Project (Re-schedule uncompleted work after ../..), MSP re-calculated future start-finish dates for the milestones correctly (in my opinion! ![]() Many thanks. |
#2
|
|||
|
|||
![]()
The Reschedule incomplete applies its own SNET constraints. Remember SNET constraints means the task can start later - just not any earlier.
|
#3
|
|||
|
|||
![]()
Duuuh... I knew I'd feel...well, like not the smartest tool in the shed.
![]() |
#4
|
|||
|
|||
![]()
You're welcome, Anna
![]() |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Evgeny | Project | 3 | 01-03-2013 06:45 AM |
How to add a fixed value to an entire column? | mikehende | Excel | 11 | 12-12-2012 02:47 PM |
![]() |
Joeb | Project | 3 | 06-25-2012 04:18 PM |
Constraints in MS Project | Antares | Project | 11 | 12-09-2011 10:55 AM |
![]() |
markg2 | Excel | 1 | 09-19-2010 12:05 AM |