![]() |
|
#1
|
|||
|
|||
![]() I think a couple of options might help: Each resource has 5 different rate tables. You could populate the rate tables with the differing rates per location. In the Task Usage view, add the Rate Table field - change the rate table and Project will recalculate cost based upon the new rate table. (Fill down works to quickly change the rate table for multiple assignments). You cannot change the value calculate in the Cost field - but you can create custom calculates in the spare Cost1, Cost2, etc fields. I hope this helps. |
#2
|
|||
|
|||
![]()
Thank you so much for your insights on this. I will try your suggestions.
Best Regards, John |
#3
|
|||
|
|||
![]()
Feel free to post back with any further questions.
|
![]() |
Tags |
custom fields, estimate, standard rate |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
ntropey87 | Word VBA | 4 | 04-20-2013 11:19 AM |
![]() |
TomT | Word | 1 | 01-10-2013 06:57 AM |
Outlook 2007 win7x32 Archive location/backup location question | michael.monaco | Outlook | 0 | 11-19-2012 02:07 PM |
![]() |
David92595 | Misc | 1 | 08-21-2011 06:02 AM |
How to set standard format for all | TDV | Word | 0 | 07-02-2011 09:41 PM |