Old 01-09-2014, 01:55 PM
JulieS JulieS is offline Formatting External Tasks in Team Planner Windows 7 64bit Formatting External Tasks in Team Planner Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I just did a quick experiment, creating a consolidated master through the pool and the External Tasks command on the Team Planner formatting ribbon had little effect. All tasks looked the same.

However, when I opened one of the sharer files, I could easily change the external (to that sharer file) task bars.

Actually - strike that. I just experimented again and in the master file, non of the tasks are considered external. I was able to change the color of the bars by changing autoscheduled bar styles, but as no tasks are external, the changing the bar style for external tasks has no effect.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Refining Team Planner View in MS Project 2010 CarolinaGamecock Project 1 11-27-2013 12:18 PM
Formatting External Tasks in Team Planner How to Improve task Detail in Team Planner ? Tray Project 9 07-07-2013 03:44 PM
Formatting External Tasks in Team Planner Team Planner-maintaining accuracy in task start and finish times david_23 Project 9 04-19-2012 08:33 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
Tasks and external files scampsd Outlook 0 11-29-2011 09:36 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:37 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft