![]() How much slack do you have in your other tasks? Are you using auto or manually scheduled tasks? How many constraints have your thrown in? Is your scheduled created with predecessors and successors? |
#2
|
|||
|
|||
![]()
1. Depends on a task (334 total, like I said): ranges from 1 to 298 days, as of right now.
2. All auto scheduled. 3. There are some firm constraints like "Start No Earlier Than" but not many at all, and they all are tied to events out of our control, e.g. the goverment in the country of operation only starts looking at land lease applications for 2014 after a certain date [I am just making the stuff up here, as an example]. 4. Yep, all but three or four tasks have both successors and predecessors. These three or four have either a successor or a predecessor but not both. Thanks! |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Critical Path Length | ketanco | Project | 5 | 03-15-2013 01:12 PM |
![]() |
ketanco | Project | 1 | 02-07-2013 06:49 AM |
critical path starting in future | ketanco | Project | 5 | 07-27-2012 02:50 PM |
![]() |
AndreT | Project | 6 | 07-27-2011 11:22 AM |
Powerpoint project schedule | L J Keane | Project | 0 | 09-14-2010 01:24 AM |