John Franklin John Franklin is offline 12 hour work days (shifts) Windows XP 12 hour work days (shifts) Office 2001 for Mac
Novice
12 hour work days (shifts)
 
Join Date: Oct 2013
Posts: 19
John Franklin is on a distinguished road
Default

All of that is correct.


Specficly were should I chech and insure the 12 hour day.
Yes, work day/shift is 7 am to 7pm. Should I tell it somewhere to tell it 7pm to 7am for the night shift?
Thanks
Reply With Quote
  #2  
Old 11-12-2013, 02:51 PM
JulieS JulieS is offline 12 hour work days (shifts) Windows 7 64bit 12 hour work days (shifts) Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

The setting is in Tools > Options. There is only one setting per project. After you create the links between your tasks, it will schedule them as needed. The default begin and end is just for tasks scheduled without predecessors and successors.

So, what is not working now?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
12 hour work days (shifts) Calendars, 12 hr shifts, 24 hrs/ 7 days John Franklin Project 3 10-30-2013 08:16 AM
12 hour work days (shifts) 36 days task at 40% effort - only "0.86 days" in resource hanvyj Project 9 07-09-2013 07:27 AM
Can Excel Deduct 30 Minutes from an 8 1/2 Hour Cell? tatihulot Excel 4 05-16-2013 04:30 PM
Calendar work days in advance paol:o Outlook 4 05-27-2012 07:23 PM
12 hour work days (shifts) Half hour added between tasks maruchi Project 1 06-17-2010 08:06 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:53 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft