Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 10-23-2013, 06:07 AM
mtbtomo mtbtomo is offline MS Project not calculating earned value correctly Windows XP MS Project not calculating earned value correctly Office 2007
Novice
MS Project not calculating earned value correctly
 
Join Date: Oct 2013
Posts: 4
mtbtomo is on a distinguished road
Default MS Project not calculating earned value correctly

Hi,

I'm new to this forum, and this has probably been posted before but I cannot understand how MSP calculates BCWP (earned value).

I thought it was commonly understood that:
BCWP = Budgeted cost x % Complete

This calculation holds regardless of whether I complete the task well before the completion date or on the completion date. i.e. if I finish the task, I can claim all the BCWP.

However, in MSP, regardless of completing all % Complete fields (physical, % work complete, % complete) and having scheduled the project, there are fully complete activities where it is not reporting the full BCWP as it should i.e. that BCWP = 100% of budgeted cost.

Having delved on the web, the only suggestion I can find is that MSP thinks BCWP is somehow time based, so I won't see 100% of my BCWP until the baseline completion date. I am not confusing this with BCWS, which I do understand is time based.

Can anyone advise?



Thanks
Reply With Quote
  #2  
Old 10-23-2013, 06:49 AM
JulieS JulieS is offline MS Project not calculating earned value correctly Windows 7 64bit MS Project not calculating earned value correctly Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Is your status date set correctly to align with the end of the completed task? I see what you report only if I have a completed task (either ahead of schedule or before schedule) if the status date is before the completion date of the task.
For example: 5 day duration task one resource assigned at $1 per hour. 40 hours of work - $40 baseline cost. I mark the task 100% complete BUT my status date is Wednesday. My BCWP is only $24. I should not have progress through Friday if today is only Wednesday.
Another scenario: 5 day duration task 40 hours of work baseline cost = $40. It is Wednesday I have recorded 24 hours of Actual Work but I set the remaining work to zero. The task is complete - my status date is Wednesday and the BCWP is $40 even though the baseline finish for the task is not until Friday.
I hope this helps.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Finding Earned Values for Different Baselines in a single project pratik6312 Project 1 08-22-2013 11:18 AM
earned value not calculating ketanco Project 3 08-16-2012 02:13 PM
MS Project not calculating earned value correctly Calculating earned value ketanco Project 3 08-13-2012 09:06 AM
MS Project not calculating earned value correctly summary task calculating from project start ketanco Project 1 01-02-2012 02:34 PM
MS Project not calculating earned value correctly How to apply budget for earned value analysis ttorneby Project 2 06-03-2010 04:52 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:14 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft