Over-allocated resource - resource holiday
 
Join Date: Oct 2013
Posts: 2
scott.hannaford is on a distinguished road
Default Over-allocated resource - resource holiday

I have set up, on resource sheet, all of the resources to be used in my project plan. I have used the resource availability field to enter when users are on holiday (set units at 0% for the duration they are off, and back to 100% for their return).



Now, for example, a resource has been indicated as Project Manager resource for 1st November 2013 to 1st February 2014, but as they are on leave 1st - 7th December, they come up as being over-allocated as they are allocated as PM during the week they are off.

Is there any way I can get Project to ignore the period when their availability is set to 0%, or is there somewhere else I need to add their holidays in?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
resource issue safaa Project 1 11-20-2012 05:41 AM
Over-allocated resource - resource holiday Resource Allocation OTPM Project 7 10-05-2012 03:40 AM
Over-allocated resource - resource holiday Allocation of resource Tray Project 3 06-01-2012 03:09 AM
Resource Status BrownHornet Outlook 0 04-12-2012 10:47 PM
Over-allocated resource - resource holiday new name for outlook resource Rayat Outlook 1 07-05-2011 04:12 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:56 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft