			Hello everybody, 
		
		
		
		
		
		
		
		
	
	I am working on a project and I've set the task type as "Fixed Work". I have scheduled my resources to work 8 hours per day. My problem is what hours to insert in Work Field > Task Form. For example, if a task has a duration of 3 days and 1 resource assigned with 200% units, what do I insert in Work field? 24 hours or 48 hours? Every suggestion and correction about the way I verge on the issue is more than welcome! Thank you in advance, Sofia.  | 
| 
		 
			 
			#2  
			 
			
			
			
			
		 
		
	 | 
|||
		
		
  | 
|||
| 
		
	
		
		
			
			 
			
			Hello Sofia, 
		
		
		
		
When you assign resources to tasks, Project will calculate one of the 3 variables: 
 For example: If a task is Fixed Work: 
 
 If a task is Fixed Units: 
 If you have a task duration of 3 days - and assign a resource at 200%, Project will calculate 48 hours of work. However - assigning a resource at 200% will usually cause the resource to be overallocated if the resource's max units are set to 100%. If you know how much work a task is, you can specify the work and Project will calculate the duration. If a task is 24 hours of work and your resources are only available 8 hours per day, the task duration should be 3 days. I hope this helps.  | 
| 
		 
			 
			#3  
			 
			
			
			
			
		 
		
	 | 
|||
		
		
  | 
|||
| 
		
	
		
		
			
			 
			
			Hi JulieS, 
		
		
		
		
		
		
		
		
	
	thank you so much for your reply and advice.It was very helpful. Regards, Sofia.  | 
| 
		 
			 
			#4  
			 
			
			
			
			
		 
		
	 | 
|||
		
		
  | 
|||
| 
		
	
		
		
			
			 
			
			You're welcome Sofia and thank you for the feedback.
		 
		
		
		
		
 | 
 
 | 
	
	
| 
		 | 
			 
			Similar Threads
		 | 
	||||
| Thread | Thread Starter | Forum | Replies | Last Post | 
		
		  Fixed duration, fixed units, fixed work, effort driven. How, why and when use it all
	 | 
	Evgeny | Project | 3 | 01-03-2013 06:45 AM | 
		
		  How to use fixed duration, fixed work and have resources/units leveled automatically?
	 | 
	Joeb | Project | 3 | 06-25-2012 04:18 PM | 
| "Set as default shape" does not work | pumpkin_feet | Excel | 1 | 02-01-2011 11:42 AM | 
| Outlook- "Type A Contact To Find" Doesn't Work | jill5545 | Outlook | 0 | 11-14-2010 08:45 PM | 
| "Outlook could not create the work file." error. All settings look good, any ideas? | Booshanky | Outlook | 0 | 08-31-2010 09:36 AM |