Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 09-23-2013, 10:48 AM
sofia sofia is offline Show multiple (near critical) paths Windows 7 64bit Show multiple (near critical) paths Office 2010 64bit
Novice
Show multiple (near critical) paths
 
Join Date: Sep 2013
Posts: 3
sofia is on a distinguished road
Default Show multiple (near critical) paths

Hi guys,

I'm using MS Project 2010. I know that in order to display multiple critical paths I should go to the File tab, click advanced options and check the "calculate multiple critical paths" box. But with this option, the critical paths are displayed all together in one gantt chart.
Is there any way i can see each near critical path separately?

Thanks in advance!!
Reply With Quote
  #2  
Old 09-23-2013, 05:57 PM
JulieS JulieS is offline Show multiple (near critical) paths Windows 7 64bit Show multiple (near critical) paths Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Sofia,

I'm sorry I don't understand what you mean by "Is there any way i can see each near critical path separately".

There is no such thing as "near critical" - task are either critical (Total Slack <=0) or not critical. Displaying multiple critical paths just traces each network path from beginning to end and calculates the tasks on that path which directly affect the end date of that path.

You can insert the Total Slack field and use that for filtering and can combine it with a date range filter but I'm not sure this will get you what you need - as I'm not sure what you need.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
tying to a critical activity ketanco Project 1 08-04-2012 05:59 AM
Show multiple (near critical) paths How to show critical task bars in different color? ketanco Project 1 05-17-2012 05:17 AM
Two motion paths iskenderbaris PowerPoint 0 04-12-2012 03:13 AM
calculate multiple critical paths ketanco Project 3 12-26-2011 09:29 AM
motion paths Cath5000 PowerPoint 0 07-29-2011 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:37 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft