Multiple projects on a single calender
 
Join Date: Oct 2013
Posts: 1
Rstaines is on a distinguished road
Default Multiple projects on a single calender

Hi guys,



I'm new to project and I'm playing around with it at the moment.

One thing that would really help me is if I could see all of the projects that were created on one calender as I run multiple projects at once.

Is there a way to set this up so I can make sure resources aren't clashing on another project?
Reply With Quote
  #2  
Old 10-03-2013, 04:33 AM
OTPM OTPM is offline Multiple projects on a single calender Windows 7 32bit Multiple projects on a single calender Office 2010 32bit
Expert
 
Join Date: Apr 2011
Location: West Midlands
Posts: 981
OTPM is on a distinguished road
Default

Hi
You can create a Master Programme Plan and insert all your own projects as sub projects into your Programme Plan.
That way you will see resource over allocations.
Hope this helps.
Good luck.
Tony
Reply With Quote
  #3  
Old 10-03-2013, 06:20 AM
JulieS JulieS is offline Multiple projects on a single calender Windows 7 64bit Multiple projects on a single calender Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm afraid just combining the project files through a master project won't directly accomplish this. Even if the resources are named exactly the same, Project will not recognize them as the same people and will not automatically flag the resources as overallocated.

You will need to create a resource pool file and then share the resources to the individual project files.

see:
http://office.microsoft.com/en-us/pr...045303641.aspx
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Multiple projects on a single calender Multiple Projects - Same Tasks JudithJubilee Project 1 05-20-2013 01:47 PM
Tracking multiple, duplicate projects sundance1 Project 3 01-16-2013 12:09 PM
Multiple projects on a single calender Unable to sync iphone calender with outlook calender!! Reltub Outlook 5 07-26-2011 02:55 AM
Multiple projects on a single calender moving data from single to multiple columns? mzimmers Excel 3 08-23-2010 08:20 AM
multiple colums under a single column RobotChicken Excel 3 01-06-2010 09:17 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2026, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2026 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft