moving tasks - retaining dependencies
Hope someone can help -
i have just completed a plan ( fully linked with predessors and sucessors) My superior has asked me to split them out into different wbs strings. When I either cut and paste or copy into a different ID line- the links do not move with the task:confused what am I doing wrong Andy |
#2
|
|||
|
|||
What version of Project are you using? it works as expected in Project 2010. I do not have 2003 around to test, but don't recall that is a change.
|
#3
|
|||
|
|||
hi julie- sorry we are using 2003
|
#4
|
|||
|
|||
I don't think this should be affecting it, but check Tools > Options, Schedule tab. Is the option "Autolink inserted or moved tasks" off?
|
#5
|
|||
|
|||
hi julie, i will check tomorrow as i am now at home ( and we ae not allowed internet access at work) - thanks
|
#6
|
|||
|
|||
Great, Keep us posted.
|
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Custom bullets not retaining settings | sleake | Word | 3 | 06-10-2013 11:41 AM |
Filter indirect dependencies | SirPercival | Project | 1 | 07-04-2012 01:03 PM |
retaining/accumulating previous slide content | kualoa1 | PowerPoint | 3 | 06-13-2012 12:55 PM |
Export Excel tasks into Outlook Tasks (2007 Version on both) | crazedmom | Excel | 0 | 12-29-2011 07:55 AM |
Moving formula range multiple cells when moving sum over one cell | FraserKitchell | Excel | 4 | 02-26-2010 10:38 AM |