Andy Francis Andy Francis is offline moving tasks - retaining dependencies Windows 8 moving tasks - retaining dependencies Office 2003
Novice
moving tasks - retaining dependencies
 
Join Date: Jul 2013
Posts: 6
Andy Francis is on a distinguished road
Default moving tasks - retaining dependencies


Hope someone can help -
i have just completed a plan ( fully linked with predessors and sucessors) My superior has asked me to split them out into different wbs strings.

When I either cut and paste or copy into a different ID line- the links do not move with the task:confused

what am I doing wrong

Andy
Reply With Quote
  #2  
Old 07-25-2013, 09:03 AM
JulieS JulieS is offline moving tasks - retaining dependencies Windows 7 64bit moving tasks - retaining dependencies Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What version of Project are you using? it works as expected in Project 2010. I do not have 2003 around to test, but don't recall that is a change.
Reply With Quote
  #3  
Old 07-25-2013, 09:07 AM
Andy Francis Andy Francis is offline moving tasks - retaining dependencies Windows 8 moving tasks - retaining dependencies Office 2003
Novice
moving tasks - retaining dependencies
 
Join Date: Jul 2013
Posts: 6
Andy Francis is on a distinguished road
Default

hi julie- sorry we are using 2003
Reply With Quote
  #4  
Old 07-25-2013, 09:30 AM
JulieS JulieS is offline moving tasks - retaining dependencies Windows 7 64bit moving tasks - retaining dependencies Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I don't think this should be affecting it, but check Tools > Options, Schedule tab. Is the option "Autolink inserted or moved tasks" off?
Reply With Quote
  #5  
Old 07-25-2013, 09:32 AM
Andy Francis Andy Francis is offline moving tasks - retaining dependencies Windows 8 moving tasks - retaining dependencies Office 2003
Novice
moving tasks - retaining dependencies
 
Join Date: Jul 2013
Posts: 6
Andy Francis is on a distinguished road
Default

hi julie, i will check tomorrow as i am now at home ( and we ae not allowed internet access at work) - thanks
Reply With Quote
  #6  
Old 07-25-2013, 10:24 AM
JulieS JulieS is offline moving tasks - retaining dependencies Windows 7 64bit moving tasks - retaining dependencies Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Great, Keep us posted.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
moving tasks - retaining dependencies Custom bullets not retaining settings sleake Word 3 06-10-2013 11:41 AM
Filter indirect dependencies SirPercival Project 1 07-04-2012 01:03 PM
retaining/accumulating previous slide content kualoa1 PowerPoint 3 06-13-2012 12:55 PM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
moving tasks - retaining dependencies Moving formula range multiple cells when moving sum over one cell FraserKitchell Excel 4 02-26-2010 10:38 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:28 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft