JulieS JulieS is offline How to help - Project 2007 - Scheduling tasks during specific windows of opportunity Windows 7 64bit How to help - Project 2007 - Scheduling tasks during specific windows of opportunity Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Making the custom calendars with "buffer" tasks is the most efficient manner. The other option is to constrain the tasks but require manual intervention.
Reply With Quote
 

Tags
calendar, meetings



Similar Threads
Thread Thread Starter Forum Replies Last Post
Sync Outlook 2010 contacts, calendar & tasks with Outlook.com & Windows Mobile 8 TimTDP Outlook 0 01-04-2013 11:30 PM
Scheduling conflicts in MS Project Antares Project 1 01-24-2012 06:36 AM
Export Excel tasks into Outlook Tasks (2007 Version on both) crazedmom Excel 0 12-29-2011 07:55 AM
Outlook completed tasks synced with Windows Mobile 6.5 ghumdinger Outlook 0 07-03-2011 07:22 AM
Scheduling of Tasks asmith1977 Project 0 01-27-2011 11:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:40 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft