hanvyj hanvyj is offline 36 days task at 40% effort - only "0.86 days" in resource Windows XP 36 days task at 40% effort - only "0.86 days" in resource Office 2010 32bit
Advanced Beginner
36 days task at 40% effort - only "0.86 days" in resource
 
Join Date: Feb 2012
Posts: 33
hanvyj is on a distinguished road
Default 36 days task at 40% effort - only "0.86 days" in resource

Hi,



I've got a set of tasks in project and I'm using the resource view to see the efforts so I can do the costing.

My manual calculations came out higher, I looked into the difference and I found at least one Task that hasn't been calculated properly.

The Task shows 36 days duration, with 40% effort for "bob bobson" - but only "0.86 days" in resource view. For another employee "John Johnson" with a 20% effort against the same task it shows the expected 7.2 days!

Bob bobsons other tasks seem to calculate appropriately, he has a 0.5 day 100% effort coming up as 0.5 days of resource.

What on earth could be causing it to pick out a specific resource and task and somehow work it out differently? I have no idea where the 0.86 days is coming from.

I'd also expect it to be spread out across the task duration (as it is for John Johnson) but it's confusingly split over two days in the middle of the 36 day window!

Has anyone come across this before?

(Project 2003)
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
36 days task at 40% effort - only "0.86 days" in resource How do I get auto-updated "number of days since specified date" on MS word? terry795 Word 16 01-07-2016 04:33 PM
36 days task at 40% effort - only "0.86 days" in resource 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Resources "Available From" Date in resource sheet bluphoto Project 3 04-05-2012 09:33 AM
How to have the "days" in other languages? Jamal NUMAN Excel 6 08-26-2011 08:34 AM
36 days task at 40% effort - only "0.86 days" in resource How to choose a "List" for certain "Heading" from "Modify" tool? Jamal NUMAN Word 2 07-03-2011 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:04 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft