JulieS JulieS is offline 36 days task at 40% effort - only "0.86 days" in resource Windows 7 64bit 36 days task at 40% effort - only "0.86 days" in resource Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What happens if you unassign bob and then re-assign? Assignments can certainly be edited in the Task or Resource usage view - do you see a pencil in the indicator column to the left of the assignment?
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
36 days task at 40% effort - only "0.86 days" in resource How do I get auto-updated "number of days since specified date" on MS word? terry795 Word 16 01-07-2016 04:33 PM
36 days task at 40% effort - only "0.86 days" in resource 5 days/week during planning & 7 days/week during implementation sanlen Project 1 06-25-2012 04:17 PM
Resources "Available From" Date in resource sheet bluphoto Project 3 04-05-2012 09:33 AM
How to have the "days" in other languages? Jamal NUMAN Excel 6 08-26-2011 08:34 AM
36 days task at 40% effort - only "0.86 days" in resource How to choose a "List" for certain "Heading" from "Modify" tool? Jamal NUMAN Word 2 07-03-2011 03:11 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:11 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft