Old 02-22-2013, 02:30 PM
JulieS JulieS is offline MS Project - Resource usage printout Windows 7 64bit MS Project - Resource usage printout Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi,

Sorry, there isn't an out of the box report with that format. The best I can suggest is to revised the column (field) order in the Resource Usage view (adding the start and finish dates to the left of the Resource name) and then copy/paste into Excel.

You'll need to then copy/paste assignment rows (task names) if the resource is working on the same task for multiple days.

Julie
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
MS Project - Resource usage printout Create a resource sheet in MS Project chabuk1 Project 8 05-01-2012 12:59 PM
Making Gantt chart and resource usage views independently viewable in MSP 2007 proj12 Project 1 02-28-2012 06:59 AM
MS Project - Resource usage printout resource leveling in ms project ketanco Project 1 12-24-2011 12:58 PM
Resource Usage sheet - options Andy Bain Project 1 11-05-2010 12:42 PM
MS Project Resource Chart fherbert PowerPoint 0 09-09-2010 12:20 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:20 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft