#1
|
|||
|
|||
![]()
Hello,
1-How do you make a 6 day calendar? I am using MS Project 2007. 2-Also, how do you make 10 hour or 12 hour workdays? Do you have to do something different if your calendar is 6 days when you do this? |
#2
|
|||
|
|||
![]()
Hello again Ketanco,
Quote:
Quote:
Same process as above but in step 5 select the working days and change the start and finish times. |
#3
|
|||
|
|||
![]()
ok thanks, and now a simpler question.
1- i created the calendar as you described but now how can i use that calendar? 2-i had entered days into my schedule before creating this calendar. now when i start using this calendar, does it mean those days wil appear the same but will mean 7 day calendar days? or will i have to multiply the previous days i entered by 5/7 to convert to 7 day work weeks? and the new days will mean based on 7 days only i assume |
#4
|
|||
|
|||
![]()
You assign the calendar in Project Information as the project calendar. You must also adjust the definition of "day" and "week" in the Schedule Options.
If you assign the project calendar it will adjust the schedule. |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Sync Outlook 2010 Calendar to Sharepoint Calendar | paankadu | Outlook | 0 | 12-08-2011 08:25 AM |
Make calendar events private in a shared calendar | Jackissimus | Outlook | 1 | 03-29-2011 04:48 PM |
Post Calendar Event to Sharepoint Calendar | rebuznow | Office | 0 | 02-18-2011 11:00 PM |
![]() |
the-ninth | Outlook | 2 | 11-03-2010 10:41 PM |
![]() |
nadall | Outlook | 1 | 09-01-2010 04:05 PM |