Hello again Ketanco,

Quote:
1-How do you make a 6 day calendar? I am using MS Project 2007.
  1. Tools > Change Working Time.
  2. Click the Create new calendar button.
  3. Name the new calendar as needed.
  4. Click the "Work Weeks tab" and click the Details button.
  5. Monday through Friday will all ready be set as working days with the default 08:00 - 17:00 working time.
  6. Select the sixth day (Saturday or Sunday).
  7. Click the "Set these days to specific working time option button and enter the working time.
Quote:
2-Also, how do you make 10 hour or 12 hour workdays? Do you have to do something different if your calendar is 6 days when you do this?

Same process as above but in step 5 select the working days and change the start and finish times.