Hello again Ketanco,
Quote:
1-How do you make a 6 day calendar? I am using MS Project 2007.
|
- Tools > Change Working Time.
- Click the Create new calendar button.
- Name the new calendar as needed.
- Click the "Work Weeks tab" and click the Details button.
- Monday through Friday will all ready be set as working days with the default 08:00 - 17:00 working time.
- Select the sixth day (Saturday or Sunday).
- Click the "Set these days to specific working time option button and enter the working time.
Quote:
2-Also, how do you make 10 hour or 12 hour workdays? Do you have to do something different if your calendar is 6 days when you do this?
|
Same process as above but in step 5 select the working days and change the start and finish times.