JulieS JulieS is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

in Project 2010:

Project tab > Set Baseline > Set baseline.
click Set Interim Plan


Copy Baseline
Intro: Baseline 1

You can then set the calculation of variance through File > Options, Advanced.
Reply With Quote
  #2  
Old 01-25-2013, 06:47 AM
joday48 joday48 is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Novice
Baseline query
 
Join Date: Jun 2012
Posts: 24
joday48 is on a distinguished road
Default

Thank you Julie, it was the interim part that threw me.
Reply With Quote
  #3  
Old 01-25-2013, 09:50 AM
JulieS JulieS is offline Baseline query Windows 7 64bit Baseline query Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You're welcome, Jo. Glad to have helped and thanks for the feedback.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
How to Query Text in MS-Excel 2010 or Import Data & Query outside of Excel? mag Excel 0 10-18-2012 11:15 AM
I didn't save a baseline joday48 Project 5 07-05-2012 02:19 PM
some work was complete at my baseline ketanco Project 1 01-25-2012 02:45 PM
Baseline query Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
Baseline query Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:23 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft