#1
|
|||
|
|||
|
Hi Julie
Thanks for replying. I am unsure how to copy my original baseline to baseline 1. I can see there is a copy function on interim plan but not the baseline option. Can you talk me through this please? I don't want to lose all the variance data I have. Thanks Jo |
|
#2
|
|||
|
|||
|
in Project 2010:
Project tab > Set Baseline > Set baseline. click Set Interim Plan Copy Baseline Intro: Baseline 1 You can then set the calculation of variance through File > Options, Advanced. |
|
#3
|
|||
|
|||
|
Thank you Julie, it was the interim part that threw me.
|
|
#4
|
|||
|
|||
|
You're welcome, Jo. Glad to have helped and thanks for the feedback.
|
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| How to Query Text in MS-Excel 2010 or Import Data & Query outside of Excel? | mag | Excel | 0 | 10-18-2012 11:15 AM |
| I didn't save a baseline | joday48 | Project | 5 | 07-05-2012 02:19 PM |
| some work was complete at my baseline | ketanco | Project | 1 | 01-25-2012 02:45 PM |
Retrieve a baseline after it's been cleared
|
fridos | Project | 2 | 05-11-2011 10:08 AM |
Help with Interim Baseline Variance
|
poyns | Project | 1 | 05-27-2010 10:59 AM |