![]() |
#4
|
|||
|
|||
![]()
Hi Julie
Thanks for replying. I am unsure how to copy my original baseline to baseline 1. I can see there is a copy function on interim plan but not the baseline option. Can you talk me through this please? I don't want to lose all the variance data I have. Thanks Jo |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
How to Query Text in MS-Excel 2010 or Import Data & Query outside of Excel? | mag | Excel | 0 | 10-18-2012 11:15 AM |
I didn't save a baseline | joday48 | Project | 5 | 07-05-2012 02:19 PM |
some work was complete at my baseline | ketanco | Project | 1 | 01-25-2012 02:45 PM |
![]() |
fridos | Project | 2 | 05-11-2011 10:08 AM |
![]() |
poyns | Project | 1 | 05-27-2010 10:59 AM |