![]() |
#4
|
|||
|
|||
![]()
Hi Jo,
I'm sorry you had to re-create the project file but from your more detailed descriptions and the information about view settings not being saved, it sounds likely that your project file did develop some corruption. I know you've resolved the issue, but you could try a test. Save the project as an XML file and then re-import (open) the XML file as a new project. Then see if you can save the view changes to the Task Sheet. Julie |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Referencing a value over 255 characters within a table PLUS strange formula behaviour | TishyMouse | Excel | 2 | 01-08-2013 09:39 AM |
Priority based levelling for split tasks having actuals | proj12 | Project | 3 | 02-27-2012 06:47 AM |
the best way to enter actuals | ketanco | Project | 3 | 12-26-2011 09:36 AM |
![]() |
Stephan Lindner | Word Tables | 1 | 09-10-2011 05:31 AM |
![]() |
projectman | Project | 23 | 11-15-2010 07:23 AM |