#1
|
|||
|
|||
|
Thanks Julie, I've created a new column with "flag1" and set the desired task to "yes", but it doesn't seem I can filter a task report based on the flag I set. I have no problem filtering the task that I want flagged, but I don't know if that option exists when I'm trying to create a report. Any ideas?
|
|
#2
|
|||
|
|||
|
Can you just print the view?
If you want to use one of the standard reports, you'll need to save the filter and apply the filter through the report definition. (click Edit in the Reports dialog). I personally am more inclined to set up the table and view and just print that than try to get the report to look exactly as I need. |
|
#3
|
|||
|
|||
|
Thanks Julie, I finally got it to work! I appreciate your help.
Trevor |
|
| Tags |
| individual, report, summary |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Costs are not adding to the summary task in cost1 column
|
ketanco | Project | 1 | 06-14-2012 03:23 PM |
summary task calculating from project start
|
ketanco | Project | 1 | 01-02-2012 02:34 PM |
Report to Show Individual Assignments
|
mikelanne | Project | 1 | 12-04-2011 11:51 AM |
| Task and Summary Durations | JR_12 | Project | 0 | 10-15-2011 05:07 PM |
| VBA code to export individual task lists to Excel | OTPM | Excel Programming | 0 | 05-24-2011 12:23 PM |