Project Days
I have project plan and i have one month in the miidel of the project out of project schedual but MS Project include that month in day caculation so how to correct that
|
#2
|
|||
|
|||
If no work is going to occur during the month - make the month non-working by changing the Project calendar. Assuming you are using Project 2010 - Project tab, Change Working Time icon.