I'm afraid I don't know what you mean by "roll ups" - are you referring to summary tasks?

By default subtask data (work, cost) values to "roll up" to summary level tasks. The advantage of summary tasks is organizational. You can create "Phases" in your project and see the cost per phase or the work per phase.

There is a setting in Task Information to "roll up" task bars to summary - that is purely visual and causes and subtask bar to appear superimposed on the summary task bar.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Roll Ups ? data roll up under unique identifier NewGirl Mail Merge 1 11-15-2012 04:47 PM
Roll Ups ? Create "Roll dice" simulation? (random number gen object?)) miiitchhh PowerPoint 1 10-14-2012 01:12 PM
Roll-Up Duration: Changing Units of Measure & Also Accuracy Of Pmacdaddy Project 3 04-20-2012 07:13 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:50 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft