#1
|
|||
|
|||
![]()
Hi All,
new to forum so thanks in advance for any help offered I have created a plan with all tasks, predecessors, resources etc. When I 'level all' it works out who should be allocated to what. However, I have some tasks I'd like to be done earlier than the task MSP is using for the first task. The reason for doing the task I want first is down to preference and there are no particular dependencies. I have tried using priority, thinking MSP would allocate the higher priority tasks before the lower, but this does not work either. I can 'fudge' it by using predecessors but this is not something I particularly want to do Thanks for any help offered |
|
![]() |
||||