Thread: [Solved] MSP level all
View Single Post
 
Old 11-19-2012, 06:23 AM
jasonjhc jasonjhc is offline Windows 7 32bit Office 2010 32bit
Novice
 
Join Date: Nov 2012
Posts: 1
jasonjhc is on a distinguished road
Default MSP level all

Hi All,

new to forum so thanks in advance for any help offered

I have created a plan with all tasks, predecessors, resources etc.

When I 'level all' it works out who should be allocated to what. However, I have some tasks I'd like to be done earlier than the task MSP is using for the first task. The reason for doing the task I want first is down to preference and there are no particular dependencies.

I have tried using priority, thinking MSP would allocate the higher priority tasks before the lower, but this does not work either. I can 'fudge' it by using predecessors but this is not something I particularly want to do

Thanks for any help offered
Reply With Quote