I have inherited this MS Project schedule. It had baseline but ,since I had to make lot of changes to schedule and add new activities, the baseline was not showing correctly. I have updated baseline where it was missing but now the baseline durations are not showing right. Is there a way to update baseline duration in line with Baseline start and finish dates?
|
Tags |
baseline, baseline duartion, duration |
|
![]() |
||||