Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 11-13-2012, 07:34 PM
Alka Alka is offline Project baseline duration Windows XP Project baseline duration Office 2010 32bit
Novice
Project baseline duration
 
Join Date: Nov 2012
Posts: 1
Alka is on a distinguished road
Question Project baseline duration

I have inherited this MS Project schedule. It had baseline but ,since I had to make lot of changes to schedule and add new activities, the baseline was not showing correctly. I have updated baseline where it was missing but now the baseline durations are not showing right. Is there a way to update baseline duration in line with Baseline start and finish dates?
Reply With Quote
 

Tags
baseline, baseline duartion, duration



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project baseline duration baseline duration, start and finsih dates ketanco Project 1 04-09-2012 09:47 AM
Project baseline duration changing one activity in a baseline ketanco Project 5 02-11-2012 07:24 AM
Project baseline duration baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM
Project baseline duration Retrieve a baseline after it's been cleared fridos Project 2 05-11-2011 10:08 AM
Project baseline duration Help with Interim Baseline Variance poyns Project 1 05-27-2010 10:59 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:58 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft