I have inherited this MS Project schedule. It had baseline but ,since I had to make lot of changes to schedule and add new activities, the baseline was not showing correctly. I have updated baseline where it was missing but now the baseline durations are not showing right. Is there a way to update baseline duration in line with Baseline start and finish dates? |
| Tags |
| baseline, baseline duartion, duration |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
baseline duration, start and finsih dates
|
ketanco | Project | 1 | 04-09-2012 09:47 AM |
changing one activity in a baseline
|
ketanco | Project | 5 | 02-11-2012 07:24 AM |
baseline duration of summary not updating. why
|
ketanco | Project | 1 | 12-14-2011 09:07 AM |
Retrieve a baseline after it's been cleared
|
fridos | Project | 2 | 05-11-2011 10:08 AM |
Help with Interim Baseline Variance
|
poyns | Project | 1 | 05-27-2010 10:59 AM |