Microsoft Office Forums

Go Back   Microsoft Office Forums > >

Reply
 
Thread Tools Display Modes
  #1  
Old 11-09-2012, 03:19 AM
lizat lizat is offline Elapsed Time, mandays &% complete Windows 7 64bit Elapsed Time, mandays &% complete Office 2010 64bit
Novice
Elapsed Time, mandays &% complete
 
Join Date: Nov 2012
Posts: 4
lizat is on a distinguished road
Default

Julie,



thank you, that seems to work. Can you explain the difference between the two complete fields?

Also related to this, if I am changing all my tasks to follow this practice of fixed work & %work complete then I am wondering how I can force the duration to "reset" to either estimated (with a ?) or actually any other chosen unit. This is a general problem that I stumble on where, for example we want to show elapsed days and the task is currently man-days, how do we force to use elapsed without loosing the current date settings.... does this make sense?
Reply With Quote
  #2  
Old 11-10-2012, 06:21 AM
JulieS JulieS is offline Elapsed Time, mandays &% complete Windows 7 64bit Elapsed Time, mandays &% complete Office 2010 32bit
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi Liz,

I'm afraid I don't follow your new question. By definition, duration is in working day - omitting non-working time such a Saturday and Sunday.

The man-hours you are referring to are usually called "work" and is based upon resources assigned to tasks. It is very possible to have a task with a fairly long duration but lower amounts of work.

The two complete fields are the % complete which is a duration field calculated = (Actual Duration/Duration)*100.

If you have a 10 day duration task, and you've complete 6 days, the percent % is 60%.

% Work complete is a work calculation:
(Actual Work/Work)*100

In most circumstances as % complete changes, % work complete would change as well. Where there may be a difference is a task that has a work contour where the task may start with 1 person but as the task progresses additional resources perform work.

I hope this helps.

Julie
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Elapsed Time, mandays &% complete complete % and physical complete % ketanco Project 3 05-25-2012 08:19 AM
IE Object: Run-time problem (the link is not clicked in run-time but not in step-in tinfanide Excel Programming 1 03-04-2012 12:05 AM
Elapsed Time, mandays &% complete % Complete (Actual) vs % Complete (Should) Carlos Maximo Project 3 12-06-2011 12:01 PM
Reporting ManDays on people not fully assigned to the Project Imagios Project 9 10-10-2011 04:36 AM
Elapsed Time, mandays &% complete Calculate elapsed time in Word table? Snvlsfoal Word Tables 1 08-11-2011 05:42 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:26 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft