![]() |
|
#1
|
|||
|
|||
![]()
Julie,
thank you, that seems to work. Can you explain the difference between the two complete fields? Also related to this, if I am changing all my tasks to follow this practice of fixed work & %work complete then I am wondering how I can force the duration to "reset" to either estimated (with a ?) or actually any other chosen unit. This is a general problem that I stumble on where, for example we want to show elapsed days and the task is currently man-days, how do we force to use elapsed without loosing the current date settings.... does this make sense? |
#2
|
|||
|
|||
![]()
Hi Liz,
I'm afraid I don't follow your new question. By definition, duration is in working day - omitting non-working time such a Saturday and Sunday. The man-hours you are referring to are usually called "work" and is based upon resources assigned to tasks. It is very possible to have a task with a fairly long duration but lower amounts of work. The two complete fields are the % complete which is a duration field calculated = (Actual Duration/Duration)*100. If you have a 10 day duration task, and you've complete 6 days, the percent % is 60%. % Work complete is a work calculation: (Actual Work/Work)*100 In most circumstances as % complete changes, % work complete would change as well. Where there may be a difference is a task that has a work contour where the task may start with 1 person but as the task progresses additional resources perform work. I hope this helps. Julie |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
ketanco | Project | 3 | 05-25-2012 08:19 AM |
IE Object: Run-time problem (the link is not clicked in run-time but not in step-in | tinfanide | Excel Programming | 1 | 03-04-2012 12:05 AM |
![]() |
Carlos Maximo | Project | 3 | 12-06-2011 12:01 PM |
Reporting ManDays on people not fully assigned to the Project | Imagios | Project | 9 | 10-10-2011 04:36 AM |
![]() |
Snvlsfoal | Word Tables | 1 | 08-11-2011 05:42 AM |