#1
|
|||
|
|||
|
Hello,
As a result of updating my schedule on some activities it automatically inserted a start no earlier than constraint, for example when i told the project to schedule unstarted activties after current data date. Is having these constraints bad for my schedule logic? especially after i do other updates later on that version? Also is there a way to remove all these alltogether at once or we can only remove these constraints one by one. (to make it start as soon as possible) by making them start as soon as possible actually is more healthy as far as the schdule loogic as long as i do the correct schedule logic instead of not correcting the wrong logic and inserting actual dates am i right? |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Update Progress breaks with constraint
|
benwimpory | Project | 1 | 03-14-2012 08:44 AM |
| splitted bars of activities | ketanco | Project | 6 | 02-11-2012 07:17 AM |
Adding or removing activities after basline
|
ketanco | Project | 3 | 01-25-2012 06:43 AM |
| Link activities and milestones between projects (2003) | jowian | Project | 0 | 11-25-2010 09:10 AM |
| OL 2010 Public Contact Activities | ibstech | Outlook | 0 | 08-05-2010 10:25 AM |