you said milestones but milestones have 0 duration. but they like to see these cost items distributed over time. so i would not do it as milestones but as activities right?
also, when i do this, they would inadvertently affect my % complete overall schedule. even if they arent part of my construction project, MS project will think it taht way. I guess there is no way to avoid it right? |