#1
|
|||
|
|||
![]()
hello,
in my schedule i have tasks which i assigned fixed costs. in the task usage view, the cost and cumulative cost are showing, between the corresponding start and finish dates. 1-BCWP and BCWS rows are not showing anything though. (although I also have a baseline). i checked both the current start and finish dates interval and the basleine start and finish dates interval but no BCWS and BCWP is visible. Why? 2-lets say I wanted to know the EV for last month, July. If it showed BCWP, I would simply add the values of BCWP for the interval of July 1- July 31 right? 3-BCWP would add up to fixed cost and would show between current start and finish dates of that activity correct? 4-BCWS would also add up to fixed cost but it would show between basline start and finish of that activity correct? |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
ketanco | Project | 3 | 08-13-2012 09:06 AM |
Calculating Profits? | MarkL | Project | 1 | 06-12-2012 07:19 AM |
![]() |
jamierbooth | Excel | 2 | 02-22-2011 03:35 AM |
![]() |
ttorneby | Project | 2 | 06-03-2010 04:52 PM |
Good commission to be earned for writing some office questions | iqnetsys | Office | 0 | 02-23-2009 05:22 AM |