![]() |
#1
|
|||
|
|||
![]()
In one of my schedules, almost half of the items have more than 80+ days of slack, on a schedule that I expect to be complete in about 4 months. This seems a lot of activities to me, and I dont think that many activities can have that much slack on a schedule that will finish in 4 months. What am I doing wrong? Does it mean they are probably missing some successor activities tied to them? By the way all my activities in the schedule have a successor, including those high slack activities.
|
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
ketanco | Project | 1 | 02-11-2012 07:23 AM |
splitted bars of activities | ketanco | Project | 6 | 02-11-2012 07:17 AM |
free slack changes when i paste from fixed cost to cost1 column | ketanco | Project | 5 | 02-03-2012 06:17 AM |
OL 2010 Public Contact Activities | ibstech | Outlook | 0 | 08-05-2010 10:25 AM |
Total Slack not updating | damianb | Project | 0 | 06-25-2010 11:48 AM |